View a markdown version of this page

Phase 6: Cutover and go-live - AWS Prescriptive Guidance

Phase 6: Cutover and go-live

Considering migration scope of 1 cluster | 100+ applications. The following table represents the cutover and go-live effort.

Activity

Effort (Hours)

Cutover planning and runbook preparation

32

Stakeholder communication and scheduling

16

DNS cutover and traffic shifting

24

Final data synchronization (stateful apps)

40

Go-live monitoring and war room support

48

Immediate issue resolution

40

Rollback execution (if needed)

24

Go-live sign-off

8