# Phase 6: Cutover and go-live
<a name="phase-6-cutover-and-go-live"></a>

**Considering migration** **scope of 1 cluster \| 100\+ applications. The following table represents the cutover and go-live effort.**


| 
| 
| Activity | Effort (Hours) | 
| --- |--- |
| Cutover planning and runbook preparation | 32 | 
| Stakeholder communication and scheduling | 16 | 
| DNS cutover and traffic shifting | 24 | 
| Final data synchronization (stateful apps) | 40 | 
| Go-live monitoring and war room support | 48 | 
| Immediate issue resolution | 40 | 
| Rollback execution (if needed) | 24 | 
| Go-live sign-off | 8 | 