Phase 3: CI/CD pipeline migration

Considering migration scope of 1 cluster | 100+ applications. The following table represents the CI/CD setup effort.

Activity

Effort (Hours)

Pipeline inventory and analysis

16

Build pipeline modifications for Amazon ECR

40

Deployment pipeline updates for Amazon EKS

56

GitOps setup (ArgoCD / Flux) if applicable

48

Pipeline testing and validation

40

Rollback mechanism configuration

24

Documentation and runbook updates

16