# Phase 1: Discovery and assessment
<a name="phase-1-discovery-and-assessment"></a>

**Considering migration** **scope of 1 cluster \| 100\+ applications. The following table** **represents the discovery and assesment effort.**


| 
| 
| Activity | Effort (Hours) | 
| --- |--- |
| Current state infrastructure documentation | 40 | 
| Application inventory and categorization | 60 | 
| Dependency mapping (internal and external) | 80 | 
| Security policy and RBAC review | 40 | 
| Storage and persistent volume assessment | 32 | 
| Network topology analysis | 40 | 
| CI/CD pipeline inventory | 24 | 
| Compliance and regulatory requirement gathering | 24 | 
| Stakeholder interviews (app owners, ops teams) | 40 | 
| Risk assessment and mitigation planning | 32 | 
| Discovery report and sign-off | 16 | 