The following worked example applies the estimation framework from the Migration lifecycle phases section to a specific scenario:
1 OpenShift cluster with 100+ applications migrating to Amazon EKS. Use this as a reference template — adjust values based on your environment.
Executive summary
OpenShift to AWS EKS Migration Scope: 1 Cluster | 100+ Applications
Parameter | Details |
|---|---|
Source Platform | OpenShift (1 Cluster) |
Target Platform | AWS EKS |
Application Count | 100+ Applications |
Base Effort Range: | 2,800 - 3,400 Hours |
Estimated Duration | 16 - 20 Weeks |
Recommended Team Size | 6 - 8 Members |
Note
The base effort range of 2,800–3,400 hours represents core migration activities. The grand total of approximately 4,255 hours includes 20% contingency reserve and 15% project management overhead applied to the base effort.
Refer to the following estimation breakdown.
Assumptions and prerequisites
The effort estimates provided in this guide are based on the following baseline assumptions. Deviations from these conditions will impact actual migration effort and timelines.
Technical environment:
Applications are containerized and running on OpenShift 4.x
Target AWS account is provisioned with required IAM permissions and service quotas
Network connectivity is established between source environments and AWS (for hybrid or on-premises migrations)
Migration approach is lift-and-shift with platform-specific adjustments; no major application refactoring required
Organizational readiness:
Business stakeholders are available for validation and sign-off activities
Team possesses foundational Kubernetes knowledge with limited Amazon EKS operational experience
Standard business hours are available for migration work, with flexibility for off-hours cutover windows as needed
If your environment differs from these assumptions, such as requiring application modernization, operating on OpenShift 3.x, or having teams with no Kubernetes experience, adjust effort estimates accordingly using the complexity multipliers and learning curve factors described in earlier sections.
Application complexity breakdown
Based on a typical enterprise distribution for 100+ applications:
Complexity Tier | Count (Estimated) | Effort Per App | Total Hours |
|---|---|---|---|
Simple | 40 apps | 8-12 hours | 320-480 |
Moderate | 35 apps | 16-24 hours | 560-840 |
Complex | 20 apps | 32-48 hours | 640-960 |
High Risk / Critical | 8 apps | 56-72 hours | 448-576 |
Complexity Tier Definitions
Simple Applications
Stateless services
Standard Kubernetes manifests
No custom operators
Minimal external dependencies
Examples: Static APIs, utility services, batch jobs
Moderate Applications
Some stateful components
ConfigMaps and Secrets dependencies
Standard persistent volume requirements
2-3 external integrations
Examples: Backend services with database connections, queue consumers
Complex Applications
Custom operators or CRDs
Advanced networking requirements
Multiple persistent volumes
Heavy integration dependencies
Custom security contexts
Examples: Data processing pipelines, middleware services
High Risk / Critical Applications
Business critical with strict SLAs
Zero or near-zero downtime requirements
Complex state management
Undocumented legacy configurations
Requires extensive rollback planning
Examples: Payment services, core APIs, customer-facing applications