Considering migration scope of 1 cluster | 100+ applications. The following table represents the post-migration suppoet and stabilization effort.

Activity

Effort (Hours)

Hypercare support (2 weeks)

160

Performance tuning and optimization

40

Cost optimization review

24

Documentation finalization

40

Knowledge transfer to operations team

48

Lessons learned and retrospective

16

Old environment decommissioning plan

24