Phase 3: CI/CD pipeline migration
Considering migration scope of 1 cluster | 100+ applications. The following table represents the CI/CD setup effort.
Activity | Effort (Hours) |
|---|---|
Pipeline inventory and analysis | 16 |
Build pipeline modifications for Amazon ECR | 40 |
Deployment pipeline updates for Amazon EKS | 56 |
GitOps setup (ArgoCD / Flux) if applicable | 48 |
Pipeline testing and validation | 40 |
Rollback mechanism configuration | 24 |
Documentation and runbook updates | 16 |