Total effort summary
Considering migration scope of 1 cluster | 100+ applications. The following table represents the total effort summary.
Phase | Hours (Range) |
|---|---|
Discovery and assessment | 428 |
Target environment setup | 520 |
CI/CD pipeline migration | 240 |
Application migration execution | 1,270 |
Testing and validation | 504 |
Cutover and go-live | 232 |
Post-migration support | 352 |
Subtotal | 3,546 |
Contingency buffer (20%) | 709 |
Grand total (base effort + 20% contingency + project management overhead) | 4,255 Hours |