Phase 7: Post-migration support and stabilization
Considering migration scope of 1 cluster | 100+ applications. The following table represents the post-migration suppoet and stabilization effort.
Activity | Effort (Hours) |
|---|---|
Hypercare support (2 weeks) | 160 |
Performance tuning and optimization | 40 |
Cost optimization review | 24 |
Documentation finalization | 40 |
Knowledge transfer to operations team | 48 |
Lessons learned and retrospective | 16 |
Old environment decommissioning plan | 24 |