Phase 1: Discovery and assessment
Considering migration scope of 1 cluster | 100+ applications. The following table represents the discovery and assesment effort.
Activity | Effort (Hours) |
|---|---|
Current state infrastructure documentation | 40 |
Application inventory and categorization | 60 |
Dependency mapping (internal and external) | 80 |
Security policy and RBAC review | 40 |
Storage and persistent volume assessment | 32 |
Network topology analysis | 40 |
CI/CD pipeline inventory | 24 |
Compliance and regulatory requirement gathering | 24 |
Stakeholder interviews (app owners, ops teams) | 40 |
Risk assessment and mitigation planning | 32 |
Discovery report and sign-off | 16 |